7 07, 2022

50Hertz: Starting shot for Ostwind 3 approval procedure

By |2022-07-07T08:19:29+02:00July 7th, 2022|GERMANY, OFFSHORE NEWS, TOP NEWS|

The application documents for the section in the EEZ relate both to the construction and operation of the approximately 24-kilometre-long submarine cable and to 50Hertz’s own transformer platform at the Windanker wind farm. The planning approval authority – the BSH – is currently checking the documents for completeness.  […]

26 01, 2022

Marco Nix: Offshore hubs and hybrid wind projects could lead the way towards an increasingly growing meshed offshore grid

By |2022-04-08T09:31:59+02:00January 26th, 2022|GERMANY, OPINIONS|

Electricity grid operators play a key role in offshore wind development. The future of wind turbines in European seas depends on the work and development of the grid. German operator 50Hertz knows this very well. Marco Nix, Chief Financial Officer (CFO) of 50Hertz, responsible for the offshore business, answers BalticWind.EU [...]

24 11, 2021

Recycling, net-zero 2050, grid development – wind industry talks in Copenhagen

By |2021-11-24T16:06:33+01:00November 24th, 2021|DENMARK, GERMANY, OFFSHORE NEWS|

Yesterday the entire wind industry came to Copenhagen to discuss the transformation of energy systems, in particular wind energy. BalticWind.EU is one of the media partners of the event. Our representatives are meeting and talking to industry representatives about the challenges facing wind energy, particularly in the Baltic Sea region. Recycling of blades and other [...]

24 11, 2021

50Hertz and Energinet sign cooperation agreement for offshore hub in Baltic Sea

By |2021-11-24T12:37:24+01:00November 24th, 2021|DENMARK, GERMANY, OFFSHORE NEWS|

Neighbouring transmission system operators 50Hertz (Germany) and Energinet (Denmark) seek to work together on the realisation of the ‘Bornholm Energy Island’ offshore hub by 2030. In the scope of the conference WindEurope Electric City 2021 in Copenhagen, CEOs Thomas Egebo of Energinet and Stefan Kapferer of 50Hertz today signed a corresponding cooperation agreement on the [...]

11 11, 2021

Cable laying for offshore wind grid connection in the Baltic Sea completed on schedule

By |2021-11-11T21:01:25+01:00November 11th, 2021|GERMANY, OFFSHORE NEWS|

50Hertz’s Ostwind 2 project reaches the next milestone. Around 170 kilometres of cable have been laid at sea and on land over the past months to connect two offshore wind farms to the German extra-high voltage grid. Now the last section of the submarine cable is being laid on schedule to complete the second of [...]