The Ministry of Economic Affairs of the State of Mecklenburg-Western Pomerania is accepting comments up to and including 28.7.2023.
The Coastal Sea section comprises the cable route starting from the connecting element of the land cable to the submarine cable section (transition joint) at the port of Vierow to the transition to the exclusive economic zone (EEZ) at the border corridor and is 77.5 kilometres long.
Anyone whose interests are affected by the Ostwind 3 project Section Coastal Sea may inspect the planning documents for a period of one month from 15.06.2023 to 14.07.2023 inclusive. The application documents for the Coastal Sea section of the Ostwind 3 grid connection project are displayed physically at the Lubmin Office and digitally on the website of the approval authority, the Ministry of Economic Affairs, Infrastructure, Tourism and Labour of the State of Mecklenburg-Western Pomerania at wm.regierung-mv.de/pfv-ostwind3-see.
Please note the opening hours at Amt Lubmin, Geschwister-Scholl-Weg 15, 17509 Lubmin in room 12:
Tuesday: 09.00 -12.00 hrs. and 13.00 -18.00 hrs. with appointment
Wednesday: 09.00 -12.00 hrs.
Thursday: 09.00 -12.00 hrs. and 13.00 -16.00 hrs.
Friday: 09.00 -12.00 hrs. with appointment
Ostwind 3 is divided into three permit sections. The first section is located in the EEZ. The public participation period for this section runs until 28 June 2023. The authority conducting the procedure in this case is the Federal Maritime and Hydrographic Agency. Public participation for the third section – the land route, transformer station and loop-in – is to take place this summer. As in the second section, the approval authority is the Ministry of Economics, Infrastructure, Tourism and Labour of the state of Mecklenburg-Western Pomerania.
Ostwind 3 is the grid connection project of the Windanker wind farm. In the future, a capacity of 300 megawatts (MW) is to be dissipated from there. For the first time, in addition to the cable systems for connecting the wind farm to the transmission grid, the offshore transformer platform (USP) is also being planned, constructed and operated entirely by 50Hertz.
Ostwind 3 is the third offshore project for the grid connection of the wind farm areas to the north-east of Rügen island (see also Ostwind and Ostwind 2 ) In 2005, the Federal Maritime and Hydrographic Agency (BSH) designated the area called ‘Westlich Adlergrund’ as a particularly suitable area for the construction of wind turbines. It has a surface of 109.2 square kilometres and is located in the German Exclusive Economic Zone (EEZ) of the Baltic Sea, i.e. beyond the 12 nautical mile zone designated as coastal waters. It is located at about 42 kilometres from the closest coast of Rügen island, and some 100 kilometres from the transition point between the submarine and land cable in the Vierow port area near Lubmin.
Source: 50 Hertz